Welcome to Schedulosophy.
Try the following quick-check for schedule quality.
First, filter out summary, milestone and level of effort activities. Then, sort by total float, early finish and early start. Your project's most critical path should be displayed immediately and unambiguously at the top of your screen. Less critical paths should appear in succession as you scroll down the page. The display can be enhanced if you group by total float. If the most critical path is not readily produced in this manner, your schedule has some problems.
Many practices can interfere with the ability to display the most critical path using this quick-check. Two of the most common are hard constraints and the presence of more than one calendar for activities along the critical path.
Scroll to the bottom of the file. Very large total floats may indicate incomplete network logic.
The objective is to craft a schedule for which the recommended quick-check produces the project's most critical path immediately and unambiguously. Practices that interfere with this functionality degrade the fidelity of the schedule as a model of the project. Practices that facilitate this functionality enhance the fidelity of the schedule as a model of the project.
Thank you for reading Schedulosophy.
Sunday, August 23, 2009
Saturday, August 22, 2009
Introduction to Schedulosophy
Welcome to Schedulosophy.
The Critical Path Method had its origins about 1940 at DuPont. CPM was virtually unknown for its first twenty years. Its use became much more widespread after the advent of computers, although it remained a manual affair for many practitioners through most of the 1980s. Desktop computing led to a succession of increasingly capable CPM programs. Yet, on the eve of CPM's seventieth birthday, an examination of schedules suggests that development of scheduling skill has not kept pace with the availability of tools or requirements of customers.
Schedulosophy is devoted to schedulers and the development of scheduling skill.
Thank you for visiting Schedulosophy.
The Critical Path Method had its origins about 1940 at DuPont. CPM was virtually unknown for its first twenty years. Its use became much more widespread after the advent of computers, although it remained a manual affair for many practitioners through most of the 1980s. Desktop computing led to a succession of increasingly capable CPM programs. Yet, on the eve of CPM's seventieth birthday, an examination of schedules suggests that development of scheduling skill has not kept pace with the availability of tools or requirements of customers.
Schedulosophy is devoted to schedulers and the development of scheduling skill.
Thank you for visiting Schedulosophy.